News | Dec. 20, 2021

FRCSW Improves Its MV-22 Readiness by 50 Percent

By Jim Markle

FRCSW Improves Its MV-22 Readiness by 50 Percent

Two years ago, Fleet Readiness Center Southwest (FRCSW) inducted its first MV-22 Osprey for a Planned Maintenance Interval-Two (PMI-2) event.
Since then, the command’s approach to PMI-2 servicing of the tiltrotor aircraft has evolved to an improved readiness level perhaps unseen in the maintenance any other airframe.

PMI-2, along with PMI-1, comprise the Navy’s Integrated Maintenance Program (IMP) that was developed to maintain the aircraft and its structural integrity.

“Our first four (PMI-2) inductions averaged 555 days and our last two deliveries had an average of 240 days,” said Michael Dixon, V-22 production manager.

“The work load standard for the PMI-2 cycle time is 482 days, however, under the Naval Sustainment System (NSS), leadership has determined 250 days to be an appropriate cycle time,” he said.

The NSS is a Secretary of the Navy initiative formed in 2018 designed to increase production and speed. 

Dixon attributed the program’s production line with meeting, and exceeding, the NSS directive.

“Our production line works diligently to highlight product constraints and delivers short and long-term resolutions to ensure production goals are achieved,” he said.

As the line becomes more established, he said, the PMI-2 turn-around time (TAT) correspondingly trends lower.

He said that some of the key factors that improved TAT included the production line gaining more experience with maintenance procedures; the hiring of aircraft examiners who have Organizational-Level experience; the qualification of two aircraft examiners to ground turn the aircraft; and implementing major changes to the PMI phases including rearranging phase requirements.

The command’s V-22 production line is staffed by 30 artisans who are mechanics, electricians, sheet metal mechanics and aircraft examiners. The line is supported by a variety of administrative positions that include production control, quality assurance, logs and records, and leadership roles.

Marine Corps squadrons fly the Ospreys to the command’s test line for PMI-2 where the aircraft undergo the induction process prior to towing to Building 333, where the maintenance cycle is performed.

“PMI requirements consist of disassembling the aircraft to evaluate the structural and wiring inspection requirements per the V-22 PMI specification,” Dixon said.
“We repair or correct any discrepancies that are noted. Then reassemble, test and troubleshoot the aircraft to ensure all systems that have been disturbed are functional and flight ready; all of which is easier said than done, as extensive maintenance is involved within this process.”

When complete, the aircraft are returned to the test line for ground turn operations and a function flight check (FCF) prior to delivery.

FRCSW delivered five MV-22s last year to its customers assigned to Marine Air Group-16 (MAG-16) at Marine Corps Air Station Miramar and MAG-39 aboard Camp Pendleton.

The command is scheduled to induct three MV-22s for PMI-2 in Fiscal Year (FY) 2022 and three during FY 23.

Meanwhile, if all goes well during its FCF, the most recent Osprey that was inducted in May is projected for delivery to Marine Medium Tiltrotor Squadron 362 (VMM-362) at MCAS Miramar in less than 227 days, three weeks under the NSS designated cycle time.
 
 
 
 
 
 
 
 

Jan. 24, 2022

FRCSW Selects its 2021 Mentor of the Year

At Fleet Readiness Center Southwest (FRCSW), Senior Chief Yeoman (YNCS) Jolyn Jones is the command’s 2021 Mentor of the Year (MOY).

Jan. 11, 2022

FRCSW Lands CNO Aviation Safety Award

In recognition of its consistent and effective airborne operations, Fleet Readiness Center Southwest (FRCSW) was recently selected to receive a Chief of Naval Operations (CNO) Fiscal Year 2020 Aviation Safety Award.

Jan. 4, 2022

FRCSW Shop Services F/A-18 Hornet Fuel Cells

The FRCSW fuel cell shop maintains all four of the airframe’s fuel tanks and one vent tank which serves as an overflow.

Dec. 20, 2021

FRCSW Improves Its MV-22 Readiness by 50 Percent

The command’s approach to PMI-2 servicing of the tiltrotor aircraft has evolved to an improved readiness level perhaps unseen in the maintenance any other airframe.

Dec. 13, 2021

FRCSW Delivers E-2D Hawkeye Ahead of Schedule

FRCSW is the Navy’s sole provider of E-2D PMI-2 events, and on December 1, the command delivered its first E-2D to complete PMI-2 under the new 220-day turn-around time (TAT).

Dec. 3, 2021

FRCSW Paints Its Last C-2A Greyhound

Last August, Fleet Readiness Center Southwest (FRCSW) inducted its last Greyhound to undergo PMI-3, the final interval in the maintenance cycle.

July 15, 2021

FRCSW Heat Shop Targets Component Readiness

Fleet Readiness Center Southwest’s (FRCSW) heat treating shop in Building 472 is the hub for the reworking of metallic and structural aircraft components that have experienced damage from hard landings or mishaps. T

July 8, 2021

FRCSW Alignment Fixtures Support Super Hornet Repairs

As Fleet Readiness Center Southwest (FRCSW) wraps up its last six F/A-18 legacy Hornet fighters to undergo the Navy’s Center Barrel Replacement (CBR) program, the command’s artisans and staff will likely increase their maintenance, repair and overhaul (MRO) services on the larger, more advanced Super Hornet. One of the MRO tools used by FRCSW in

June 22, 2021

Last F/A-18 for Center Barrel Replacement (CBR)

FRCSW Inducts last F/A-18 for Center Barrel Replacement (CBR) Program

April 16, 2021

FRCSW Paint Shop Adds Finishing Touch to Fleet Aircraft

Of the various maintenance schedules, repairs and preparations that aircraft undergo at Fleet Readiness Center Southwest (FRCSW), one procedure is common to all: painting....

No items to display